Dana Drilling Co. has reached an overall physical progress of ca. 54% for the EPD project in phases 15&16. For the period of the drilling operation until March 2011, it was totally drilled about 32,000 meters comprising of ca. 19,700 meter drilling in phase 15 and 12,300 meter in phase 16.
Following this success the drilling of the second appraisal well SPD-16-08 in phase 16 will be soon ended by logging service, after drilling of the first appraisal well SPD-15-08 in phase 15 has been finished in the last summer. In the phase 15, currently the 12-¼” hole section is under drilling program to the planned TD.
|