According to the latest records by Dana Drilling Co., the overall physical progress of EPD project in the south pars gas field phases 15 & 16 has reached 77% on beginning of January 2012. For this period a total depth of 64,500 meters have been drilled so far and 5 wells have been completed consequently. It is forecasted that the drilling operation would end by August 1st 2012.
|