منوی دینامیک
Letest News
  Dana Geophysics Company takes part in International Geophysical Conference and Exhibition in Istanbu
  Bahar 2D Seismic Project Is Concluded Between NIOC Exp. Directorate and Dana Geophysics Co.
  A consortium including Dana Geophysics Co. was introduced as winner of Nasr-Abad gas storage tender
  Dana Geophysics Co. is introduced as the winner of 2D Seismic Survey & Processing of Golestan tender
  Comprehensive Study of Forouzan Oil Field Reservoirs Is Awarded To Dana Geophysics Co
  Dana Geophysics Company is announced as winner of Bibihakimeh 3D Survey
  Gas Hydrate Study in Oman Sea, A New Project Awarded To Dana Geophysics Company(DGC)
  Ahwaz 3D Seismic Survey Operation Starts
  Contract of "Persian Gulf Pearl Program" was signed between IOOC and Joint Venture of RIPI and DGC
  IMS Certificate extends for another year in Dana Geophysics Company
 
Finish of Tang-e-Bijar complementary 2D seismic acquisition

“Tang-e-Bijar complementary 2D seismic acquisition” finished on January 2, 2011 with 15229 shot points fired. It was interesting that the project just finished 34 days ahead of contractual committed end date.

Tang-e-Bijar project was located in a mountainous area consisted of 2826 sq km land of 2 provinces and 5 townships. Due to exigencies of mountainous area, the project utilized 1670 hours of flight operations performed by helicopters. The project was performed well-done enough that project client, ICOFC, has assessed performance of Dana Geophysics Company excellent.

Considering successful completion of “Tang-e-Bijar complementary 2D seismic acquisition,” it was a great honor for Dana Geophysics Company to fulfill such work.

 