منوی دینامیک
Letest News
  Comprehensive Study of Forouzan Oil Field Reservoirs Is Awarded To Dana Geophysics Co
  Dana Geophysics Company is announced as winner of Bibihakimeh 3D Survey
  Gas Hydrate Study in Oman Sea, A New Project Awarded To Dana Geophysics Company(DGC)
  Ahwaz 3D Seismic Survey Operation Starts
  IMS Certificate extends for another year in Dana Geophysics Company
  Exploration Directorate of NIOC Appreciates successful finish of Tang Homam 2D Survey
  Dana Geophysics Company was introduced as winner of Ahwaz 3D acquisition tender
  Tang-e Homam 2D Seismic Project Finished Successfully
  Dana Geophysics Completed the 3D Seismic Data Processing project of Ramshir Oilfield
  Finish of Tang-e-Bijar complementary 2D seismic acquisition
 
Tang-e Homam 2D Seismic Project Finished Successfully

Tang-e Homam 2D seismic project of Dana Geophysics Company successfully finished last week on June 8, 2011 that is about more than one month ahead of contractual end date.

Some parts of the project which were in mountainous areas have been executed by means of helicopters. Also the project was generally located in boundary regions, which include mine fields and unexploded ordnance that fortunately the project finished with more than 1’100’000 man-hours work without incidents.

Within 17 months of project execution time, 14534 shot points fired along with 961 km of acquisition lines. Successful completion of such work is of great honor for Dana Geophysics Company.

 